ELDECO LA VIDA BELLA · SEC 12
UP-RERA UPRERAPRJ136219/04/2024 DECLARED COMPLETION 16-01-2029 STATUS LEDGER OPENED 18 JUL 2026 NO INVENTED CONSTRUCTION-PROGRESS CLAIMS ASK FOR THIS WEEK'S SITE PHOTOS ON WHATSAPP
ENTRY / 2026 / LA VIDA BELLA — CONSTRUCTION STATUS

Construction status, tracked honestly — not invented.

Most "construction status" pages print a confident percentage nobody measured. We won't do that. This page gives you the one number that is actually verified — the RERA-declared completion date — explains exactly what that date legally means, and keeps a dated ledger of what our desk can honestly confirm as it comes in. When we don't know the on-site stage, we say so, and we ask the founder for this week's photos instead of guessing.

OPENED 18 JUL 2026 · COMPLETION DATE: UP-RERA REGISTRY · CONSTRUCTION STAGE: LEDGER BELOW, UPDATED HONESTLY

The declared completion date — and what it legally means

Verified · UP-RERA registry LVB / DECLARED COMPLETION

16-01-2029 — the date construction is registered to finish by

Registration UPRERAPRJ136219/04/2024 · registered 26-04-2024 · project duration 60 months from start date 01-02-2024 · promoter of record ELDECO REAL ESTATE LIMITED. This is the completion date the promoter filed with the regulator — the anchor for everything else on this page. The full registry record →

Desk note · general RERA mechanics, not legal advice LVB / TWO DATES, NOT ONE

The registry date and your agreement date are usually the same date — confirm it is

The 16-01-2029 figure above is what the promoter declared to UP-RERA. The date that is legally binding on the promoter for your specific unit is the completion clause printed in your own registered Agreement for Sale — ordinarily aligned to the RERA filing, sometimes with a stated grace period added on top. Read that clause yourself before you plan a move-in date around any figure, including this one.

Verified · Section 18, RERA Act 2016 LVB / IF POSSESSION IS DELAYED

The remedy the law gives you

If a promoter fails to hand over possession by the date committed in the Agreement for Sale — and the delay isn't a genuine force-majeure case — an allottee can withdraw and claim a full refund with interest and compensation, or stay in and collect interest for every month of delay until possession is actually handed over. General law; not a claim about this project's own timeline.

Verified · Section 6, RERA Act 2016 LVB / EXTENSIONS ARE NARROW

Registration can be extended — but only once, and only for force majeure

A promoter genuinely unable to complete on time for reasons beyond its control can apply to the authority for an extension of the registration, capped at one year in aggregate. Outside a genuine force-majeure case, a missed declared-completion date is exactly the trigger Section 18 exists for.

The five towers being built

Developer-stated · official brochure LVB / WHAT'S UNDER CONSTRUCTION

Bellissimo 1–3, Magnifico 1–2 — five towers, all G+22

Per the developer's official brochure master plan, the project comprises five towers — Bellissimo 1, 2, 3 and Magnifico 1, 2 — all G+22, on land the brochure states as 14,998 sq. mtr (~3.71 acres). This is what the completion date above refers to. Full unit-type table by tower → · Plot and layout detail →

Eldeco La Vida Bella tower exterior — artistic render from the developer's brochure
Tower exterior — artistic render, developer's brochureNot a construction-progress photograph

The status ledger

A dated log, not a percentage we made up. Every entry below carries a date and a tier. New entries get added above the oldest one as our desk has something verified to report — nothing here is backfilled or rewritten after the fact.

Desk note · page opened

Page opened; current on-site stage not yet independently verified — ask for this week's photos on WhatsApp. The founder can send actual site photos on request; we will post them here, dated, the moment we have them rather than describing a stage nobody has walked.

Verify the completion date yourself — four minutes, no login

Don't take this page's word for the date either. Here is the same four-minute check we run ourselves, aimed specifically at the completion date and the promoter's own progress filings.

  1. Open up-rera.in and go to the Registered Projects search.
  2. Search "La Vida Bella" — or paste the number UPRERAPRJ136219.
  3. Open the project summary and find the proposed completion date (or revised completion date, if the promoter has since sought a force-majeure extension) — match it against 16-01-2029 as printed on this page.
  4. Open the filings for quarterly progress returns (QPR) — this is where the promoter's own, legally-filed construction-status updates live, not on any marketing page, ours included.
  5. Before relying on any date for your own planning, match it against the completion clause in your own registered Agreement for Sale — that is the version the law measures a delay against.

How RERA milestones actually work

General mechanics of the law your booking sits inside — not a claim about where this specific project stands today, and not legal advice.

Verified · RERA Act 2016, general provisions LVB / THE MECHANICS, PLAIN
How a RERA completion date gets set, tracked and enforced — general law
MechanismWhat it means
Registration & declared completionBefore booking can be offered, a project must register with the state authority, filing its land title, sanctioned plans and a completion date the promoter commits to. That date is what shows on the registry — and at the top of this page.
Quarterly progress updatesPromoters are required to keep the project's status current on the state RERA portal at regular intervals, covering approvals and construction progress. It is public, filed by the promoter — check the live filing for this project rather than trusting any single page, including this one.
Force-majeure extension (Section 6)If a promoter is genuinely unable to finish on time for reasons beyond its control, it can apply to the authority for an extension of the registration — capped at one year in aggregate — before a missed date is treated as a plain delay.
The delay remedy (Section 18)Once the date committed in your own Agreement for Sale passes without possession, and it isn't a genuine force-majeure case, you can exit with a full refund plus interest and compensation, or stay and collect interest for every month of delay until you actually get the keys.

General provisions of the RERA Act, 2016, summarised for orientation — not legal advice and not specific to this project's current status. For a delay dispute, the authority's adjudicating officer or the appellate tribunal, not this page, is where it gets decided.

Why this page exists: a possession date is a promise with a legal remedy attached to it — but only if you know the mechanism and can point to the exact clause in your own paperwork. Verification first, enthusiasm second — the same rule as everywhere else on this site. Verify it together on a call →

Frequently asked

What is the possession date of Eldeco La Vida Bella?

The UP-RERA registry lists a declared completion date of 16-01-2029 for UPRERAPRJ136219/04/2024, against a 60-month project duration that started 01-02-2024 — that is the RERA-verified figure to plan around. The date that is legally binding on the promoter for your specific unit is the one printed in your own registered Agreement for Sale, which is ordinarily aligned to this filing; confirm the exact clause before you plan your own move.

What is the construction status of Eldeco La Vida Bella?

We have no independently verified construction-progress figure to give you, and we do not invent one. What exists instead is the dated status ledger on this page, updated only when our desk has something verified to add, plus a standing offer: ask on WhatsApp for this week's site photos and we will get them to you from the ground.

Is Eldeco La Vida Bella RERA approved?

Yes. It is registered with UP-RERA under UPRERAPRJ136219/04/2024, registered 26-04-2024, promoter of record ELDECO REAL ESTATE LIMITED. You do not need to take our word for it — the self-verify walkthrough on this page shows you how to pull the same record yourself at up-rera.in in about four minutes, no login required.

What happens if possession is delayed under RERA?

Under Section 18 of the RERA Act 2016, if a promoter fails to complete or hand over possession by the date committed in the Agreement for Sale, and the delay is not due to a genuine force-majeure event, an allottee can either withdraw from the project and claim a full refund with interest and compensation, or stay in and receive interest for every month of delay until possession is actually handed over. This is general law, not a claim about this specific project's timeline.

How do I verify the Eldeco La Vida Bella RERA completion date myself?

Go to up-rera.in, open Registered Projects, and search La Vida Bella or the number UPRERAPRJ136219. The project summary shows the registered date, the declared completion date and the promoter of record — match those fields against what is printed on this page. The whole walkthrough takes about four minutes and needs no login.

Get this week's site update

Name and number — our desk replies on WhatsApp with whatever is verified this week, photos included where we have them.

Received.

The desk will reply on WhatsApp shortly — with sources attached.

By submitting you consent to be contacted and to your details being shared with the developer/promoter to process your enquiry. Nothing is auto-sent; no payment is ever requested online.

Disclaimer. This website (eldecoflats.com) is not the official website of the developer and is independently owned and operated by Vidastu Advisory, a real-estate agent registered with the Uttar Pradesh Real Estate Regulatory Authority — UP-RERA Agent Reg. No. UPRERAAGT000309/01/2026 — acting as an authorised channel partner for this project. It is published for information and booking-assistance purposes.

Project: "Eldeco La Vida Bella", Plot GH-02C, Sector 12, Greater Noida West (Noida Extension), tehsil Dadri, district Gautam Buddha Nagar, Uttar Pradesh · UP-RERA Registration No. UPRERAPRJ136219/04/2024 (registered 26-04-2024; declared completion 16-01-2029) · Promoter of record: ELDECO REAL ESTATE LIMITED (the developer's official site is eldecogroup.com). Verify every registry fact directly at up-rera.in. "Eldeco" and all related marks are the property of their respective owners, used here only for identification; we claim no ownership, sponsorship, approval or endorsement.

Nothing on this page is legal advice, an offer, or a contractual commitment. The RERA-mechanics explainer above summarises general provisions of the Act, 2016 and is not specific to this project's current status. Construction-status entries in the ledger above are dated and tiered at the time they are added and may be superseded by later entries or by the promoter's own filings, which prevail. Our fee comes from the developer; buyers pay us nothing. By submitting your details you consent to be contacted about this project and to your information being shared with the developer/promoter to process your enquiry. Never pay any individual — pay only the promoter entity named in your registered agreement, and never more than 10% of the price before a registered agreement for sale (Section 13, RERA Act 2016).